IEC 61850 comprises various parts and defines not only the data structure
and communication of IEDs (IEC 61850 station bus level), but also the digital transfer of converter signals based on Ethernet (part 9-2).
The evaluation of the converter values is done by Merging-Units (IEC 61850 process bus level). Latest findings aim at a combination of process bus IEC 61850-9-2 with real-time Ethernet, a new development in the field of industry automation. RWE Energy AG has launched a F&E-Project regarding "Intelligent Switch Bay" , which also requires special tasks from the voltage regulator REG-D. More on this subject can be found in our special edition IEC 61850 Novelty: Client functionality for all family members. 
 |