Performance increase in the distribution grid

Our Low Voltage Regulation System LVRSys® as a useful tool for the future

Grid congestion causes rejection of PV connection requests by grid operators

Due to economic unreasonableness, grid operators are rejecting applications to connect PV systems in the low-voltage grid more often. The responsible grid planners are guided by the connection guideline VDE-AR-N 4105, in which decentralized generation facilities may only raise the voltage level in the low-voltage grid by 3% compared to the previous situation. Potential photovoltaic plants are thus not realized, despite existing technical transmission capacity.

The current-carrying capacity of the grids is rarely approached by complying with the directive.

The following voltage drop analysis demonstrates the limitations of integrating photovoltaic systems into the low-voltage grid using traditional calculation methods and outlines a way out using the Low-Voltage Regulation System LVRSys®.

Voltage increase due to grid integration of PV systems

According to the fundamentals of electrical science, the voltage drop of power along a line can be calculated using the following formula:

Figure 1 illustrates the normalized voltage drop (3%) from the line impedance (line length and cross-section) depending on the power. Aluminum cables with cross sections of 4 x 150 mm² and 4 x 240 mm² are frequently used in the European low-voltage grid. These cables may be loaded up to a length of 120 m or 140 m at 100 % (250 kW / 186 kW) and at a length of 500 m at the end of the cable only with 42 kW or 65 kW, respectively, in order to comply with the 3 % criterion. After 500 m, the load of the cables is only approx. 25 %. Therefore, after a short cable length, the limiting parameter for the connection of distributed generation plants is no longer the current carrying capacity, but the voltage maintenance.

Figure 1: Permissible active power according to cross-section and cable length for a voltage drop of 3%
Figure 2: Permissible active power according to cross-section and cable length for a voltage drop of 9%

Using a LVRSys® low-voltage control system with an exemplary control range of ±6%, the permissible voltage drop that must be maintained increases from 3% to 9% (Figure 2). The 4 x 150 mm² or 4 x 240 mm² cables can be 100% loaded by using the controller up to a length of 350 m or 390 m, respectively, without violating the 3% criterion. The grid integration of decentralized generation facilities can therefore be increased up to the technical utilization limit (current carrying capacity) of the cables. For longer cable sections, the grid integration can be increased 4-fold by using controllers.

This example illustrates that the LVRSys® is a building block for low-voltage grids to advance the energy transition in a cost-effective manner.

Do you have questions about our LVRSys®?

Contact us!


Contact

You might also be interested in

REGSys® Parallel Regulation of Transformers

The regulation of transformers with tap changers is an essential subject within the field of power supply and distribution. Today these tasks are accomplished electronically with high regulation quality. Digital regulators, such as the freely programmable REGSys® voltage regulator system, are in use.

Read more

Cost efficient management of digital secondary substations: Earth fault indicator EOR-3DS as digitisation unit for secondary substations

Digital secondary substations are becoming a key element for distribution system operators in terms of automation, monitoring, and efficient operations of their networks. Read this technical report about the EOR-3DS in its role as digitisation unit for secondary substations.

Read more

Angle determination of voltage and current harmonics in practice

Today's devices and equipment such as switched-mode power supplies, frequency converters, regulated drives, charging devices for e-mobiles or LED lighting work internally with high clock frequencies in order to regulate power efficiently. These can lead to both conducted and field-bound (coupled) influences in the energy grid. In this technical report, we explain how you can detect these sources of interference in the grid using suitable measuring technology.

Read more

All „Supra“ with your grid?

Today's devices and equipment such as switched-mode power supplies, frequency converters, controlled drives, charging devices for e-mobiles or LED lighting work internally with high clock frequencies in order to regulate power efficiently. These can lead to line-borne as well as field-borne (coupled) interference in the power grid. In this technical report, we explain how you can detect these sources of interference in the grid using suitable measurement technology.

Read more

Contact request:



Your data is being processed

a-eberle kontakt newsletter ×

Our seminars &
webinars

► Register here!

x