+++ ONLY UNTIL DECEMBER 31st: PQ-Box Trade-In Promotion +++ Only a few days left to save on your PQ-Box order +++ Click here for all further information! +++

+++ ONLY UNTIL DECEMBER 31st: PQ-Box Trade-In Promotion +++ Only a few days left to save on your PQ-Box order +++ Click here for all further information! +++

+++ ONLY UNTIL DECEMBER 31st: PQ-Box Trade-In Promotion +++ Only a few days left to save on your PQ-Box order +++ Click here for all further information! +++

Integration Guide for the Metering of a Power Plant According to the Requirements for Generators (2016/631) RfG

Information Letter No. 24

Following the expiry of the transitional periods for the certification of generation units according to the VDE connection guidelines in the German area, numerous questions repeatedly arise regarding the correct installation of the fault recorder system required to demonstrate compliance according to the European Directive for Generation Units (2016/631). The following guide should help to find out, on the one hand, which special features are required and, on the other hand, which components must be selected for the system to work.

Testing With High-Precision Measurement Technology Is Necessary.

Planning errors in the construction of large-scale generation units often lead to increased costs and delayed certification. Admittedly, this is also due to a very complex issue. According to chapter 6.4 of VDE-AR 4110, fault recording and power quality monitoring are recommended for transfer stations in justified cases. For systems in the individual verification procedure, the requirement is formulated in more detail. In that case, a recorder must be installed to “be able to continuously check the requirements for dynamic mains support in live operation, if compliance with the requirements for dynamic mains support could not already be demonstrated by measurements during commissioning” [standardised extract from VDE-AR 4110]. This measurement test must, of course, be carried out using suitable, high-precision measurement technology, tested in accordance with the standard.

The individual verification procedure required for some systems with the installation of a fault recorder for compliance monitoring, to be carried out by an accredited certification body, requires a high degree of coordination between all actors involved. First of all, the appropriate measurement technology, which meets all requirements, must be selected for the verification procedure. In addition, the necessary expertise is required for the correct installation of the measurement technology. Furthermore, certain requirements for the transducers used must be taken into account, as well as the necessary verification to ensure the required accuracies (DAKKS calibrations) of the technologies used. With regard to the subsequent compliance check, an easy-to-implement half-yearly data exchange must be ensured.

This guide provides a practical overview of the most important components to ensure and facilitate a reliable measurement chain.

VDE-AR 4110
Figure 1: Necessary components for a power plant in the individual test procedure

Requirements for Fault Recorders

According to Annex F of the connecting guideline, the fault recorder requires certification according to class A of IEC 61000-4-30 (Ed. 3) to ensure safety and accuracy of measurement. Annex F requires the sampling frequency of the recorders to be at least 1 kHz. However, for the evaluation of voltage and current supraharmonics in the frequency band range of 2-9 kHz, which is subdivided into 200 Hz bands according to DIN EN 61000-4-7, it is essential to provide higher sampling frequencies for the measurement. Therefore, a minimum sampling frequency of 20 kHz is required to be able to perform the required measurement according to FGW TR 3.

In order to ensure consistent data recording even in case of failure and power failure and to document the reaction of EZA even in case of power failure, a UPS system for the measuring device and additional components such as the communication infrastructure (switches, gateways, servers) is recommended in any case. Of course, there must be no loss of parameters and data in the power quality measuring device used, even in a de-energised state. This must be ensured by the measuring device and the configuration. Reliable data is required especially in the event of a fault.

In this context, time synchronisation plays an important role. Therefore, an external synchronisation, e.g. via GPS, is necessary to ensure a maximum accuracy in the overall system of up to 25 µs. The accuracy of the entire measurement chain is of great importance in the detection process.

However, the accuracy of the measurement result does not only consist of a high-precision measuring device with a maximum deviation of 0.1% and the corresponding verification, but the total error of the entire measurement chain is significantly influenced by the transducers used.

Thus, for example, the transformers used must also be capable of transmitting supra-harmonics without error. In the medium and high voltage range, there is already a wide variety of transformers on the market that can also transmit frequencies in the 2-9 kHz range with deviations <0.1%. Especially in DCA systems with DC link controlled power supply, dominant clock frequencies are often responsible for feedback effects such as increased noise generation, as can be seen in figure 2.

This requires that the fault recorder supports a wide variety of transducer technologies with respect to the input signals.For example, transducers that can pick up the higher frequency range of 2-9 kHz are usually equipped with 3.25 V/√3 outputs instead of 100 V/√3.In any case, the impedance ratio between the transducer output and the encoder input must match. Therefore, it is necessary to check the respective impedance requirements prior to acquisition and to clarify in advance the necessary data for the measuring instrument and the selected measuring input with the supplier of the transducer to be used.

VDE-AR 4110 windkraftanlage
Figure 2: Fingerprint of a wind power plant in the range 2-9 kHzb

Measuring With Sensors Simple and Highly Accurate

The PQI-DE supports a wide range of combinations and installation situations, both in the area of voltage measurement and through the various current measurement possibilities, also in the area of retrofitting, e.g. through the high-precision Rogowski inputs for current measurement.

  • 100 V 2 MOhm || 25 pF
  • 100 V / 400 V / 690 V 10 MOhm || 25 pF
  • 3.25 V 2 MOhm || 50 pF for small-signal transducers according to IEC 61869-11 (SELV)
  • 4 current inputs for transducers 1 A/5 A (MB max. 10 A)
  • 4 current inputs for protection transformers 1 A/5 A (MB max. 100 A)
  • 4 current inputs for Rogowski clamps (Input 350 mV)
  • 4 current inputs for current clamp meter (AC converter 0.5 V input)

DAKKS Calibration Required

To ensure and guarantee the accuracies, a DAKKS calibration is required before delivery and installation of the measuring device. The standard factory calibration is not sufficient for certification.

For this reason, A. Eberle GmbH & Co. KG requires an extended DAKKS calibration by a certified laboratory, also in the field of supra-harmonics for the measuring devices.

According to the connection guideline, the certification body has the task to evaluate the measurement data at least every six months. For this purpose, a simple and seamless data exchange must be ensured. In addition, the system must be able to provide a suitable software solution to evaluate the data. It is important to use a system with simple, flexible and open interfaces, which can be adapted to on-site conditions and communication solutions.

VDE-AR 4110 dakks

System Requirements

Simple
In the simplest case, the data transfer from the measuring device to the certification body must be done by inserting an SD card and copying the entire internal memory. The readout in a power quality evaluation software works similarly in a plug & play procedure.

Flexible
From simple data transfer by inserting an SD card to automated data transfer via mobile radio, SHDSL or Ethernet: always trouble-free, even with poor connection quality. Diverse and customisable system solutions should be possible.

Open
Comtrade or PQDIF as standard via IEC 61850, IEC 60870-5-104 or Modbus. The measuring instruments and the WinPQ system of A. Eberle GmbH & Co. KG have numerous open standard interfaces and protocols for the transmission of measurement data.

WinPQ: Automatic Compliance Check of Power Plants Using FRT Curves

Power plants have to perform dynamic grid support in accordance with the European Grid Code. This requirement applies mainly in case of faults and indicates that generating plants have to comply with the following requirements in case of symmetrical and asymmetrical grid faults:

  • There shall be no disconnection of the generating plant in case of undervoltage or overvoltage events within the limits specified according to the type of plant and (FRT curve).
  • The grid support requirement also applies in case of several consecutive faults.
  • The plants must maintain the grid voltage during the grid failure by injecting a reactive current (reactive power). The reactive current must be supplied in both positive and negative sequence systems depending on the type of fault.

To check the requirement in the various systems, the WinPQ Power Quality system software from version V. 6.2 onwards offers an optional AddOn for automatic fault classification via the FRT curves already present in the system. It is possible to store each measuring point with an FRT curve corresponding to the type of installation. On the one hand, this offers the possibility to classify faults directly over a period of time, e.g. one year (Figure 3). On the other hand, it also allows for an active alarm. In this case, the system only sends an alarm to the plant operator or the designated certifier by e-mail when the value falls below or exceeds the specified characteristic curve, as shown in Figure 4.

It should be noted that the FRT curves provide for a fault evaluation of up to 60 seconds. Therefore, the fault recorder used must be able to provide the measurement data as a 10 ms rms value in any case and this even in the case of several consecutive faults, as this is expressly required by the Grid Code. In this context, it is strongly recommended to calculate the rms value in accordance with IEC 61000-4-30 – Class A Ed. 3 in order to allow uniform and comparable evaluations from a normative point of view.

Figure 3: Interactive classification according to pole error type 1-2 of the FRT curve
Figure 4: FRT curve for installation type 1

Example of the Application of an ACA According to VDE-AR

The certification body involved in this project relies on automated data transfer in a standard Comtrade format for automated fault evaluation. Figure 5 shows that in the event of a mains failure, the data from the fault recorder is recorded in the measuring device using the VDE-AR 4110 template approved by the certifier. Subsequently, the data is automatically generated by the WinPQ system software installed on site (SSH) and sent directly to the server of the certification body. In the event of a failure, the server directly evaluates the data and checks whether the power plant is operating in a grid-serving manner.

Figure 5: Implementation of a power plant in accordance with VDE-AR

The customer also has the possibility to visualise and evaluate the measured power quality values at any time by means of a clear report. In case of communication difficulties due to an unbuffered network, the customer has the option of reading the data directly from the measuring device via an SD card and providing this data. In parallel, the high-precision measured values U, I, P, Q as well as the daily statistics of the PQ events are transmitted via a standard protocol – in this case IEC 61850 – to a SCADA system for on-site display and also for issuing alarms.

VDE-AR 4110 winpq pqi
Figure 5: Implementation of a power plant according to VDE-AR

Conclusion

Through a uniform and coordinated procedure of all persons and companies involved, a high degree of cost savings and efficiency can be achieved for both the certifier and the operator of the power plants.

We will be happy to assist you during this process with our safe and certified class A (Ed. 3) measuring devices PQI-DE and PQI-DA smart in combination with the WinPQ power quality system software as well as our experience in the field of services for the operation and installation of measuring devices.

Please contact us in good time before selecting the components – we will be happy to help you.

VDE-AR 4120
monitoring-software-power-quality VDE-AR 4120
VDE-AR 4120

Author
Fabian Leppich, Product Manager Power Quality System

Need More Information?

Contact Us!


Contact

Info-Letters

Click Through Our Info Letter Series

News From the Product Group

News

General Knowledge

Harmonics

Harmonics are waves whose frequencies are an integer multiple higher or lower than those of the fundamental oscillations. They arise due to non-linear loads in the grid when the electrical voltage is distorted due to various influencing factors. Learn more about harmonics in this article!

Read more

Training Video

»PQMobil« Training Video 6: Presentation of WinPQ mobile 7.1

In this video we introduce you to all the new features & functions of the latest version of the analysis software »WinPQ mobil 7.1« for our portable power quality analysers. Enjoy the video and the new possibilities with your PQ-Box from A. Eberle.

Read more

Blogpost

International Partner Week 2024 – a Look Back

Our International Partner Week 2024 - many old friends and new faces were our guests, it was a pleasure.

Read more

Training Video

»PQMobil« Training Video 5: Trigger and Fault Record Settings

Discover the best trigger settings for your »PQ-Box« to accurately record network disturbances. The video shows how to configure the half-cycle, oscilloscope, and transient recorders to reliably capture essential measurement data.

Read more

Webinar

»PQSys« Webinar: PQ-Monitoring & Feeder Current Measurement With PQSys

Webinar recording from 2024-08-06: »PQSys - PQ-Monitoring & Feeder Current Measurement with PQSys«.

Read more

Blogpost

PQ-Box Trade-in Promotion: Only From 1 September to 31 December 2024

For a limited time: Receive a discount for the trade-in of your PQ-Box 100 or a comparable external old device (3-phase power quality analyser). Click here for further information!

Read more

General Knowledge

Voltage Monitoring

Find out everything you need to know about voltage monitoring in this article. What is voltage monitoring, why is voltage monitoring essential for both energy supply companies and industrial companies and how is it implemented in compliance with standards?

Read more

General Knowledge

What Is Load Profile Measurement/Power Measurement?

This article explains the definition and difference between load profile measurement (RLM), power measurement and measuring the standard load profile. These are important methods for accurately recording energy consumption in commercial, large industrial plant as well as in the public energy grid.

Read more

Training Video

»PQMobil« Training Video 4: Create and Configure PQ Reports With Software WinPQ Mobil

This video explains everything about creating and configuring power quality reports with »WinPQ mobil«.

Read more

Webinar

»PQMobil« Webinar: Grid Analysis in Public & Industrial Power Grids With A. Eberle PQ-Boxes

Webinar recording from 2024-02-22: »PQMobil - Grid Analysis in Public & Industrial Power Grids with A. Eberle PQ-Boxes«.

Read more

Webinar

»PQSys« Webinar: PQ-Monitoring & Feeder Current Measurement in Low-Voltage Grids

Webinar recording from 2024-04-17: »PQSys - PQ-Monitoring & Feeder Current Measurement in Low-Voltage Grids«.

Read more

Training Video

»PQMobil« Training Video 3: Usability & Functions of the PQ-Box App

This video gives you an introduction to the usability and functions of the »PQ-Box App« for our portable power quality analysers.

Read more

Training Video

»PQMobil« Training Video 2: Menu Navigation and Operation of the PQ-Box

In this short introductory video, we present to you how to navigate and operate our portable power quality analysers »PQ-Box 150«, »PQ-Box 200« & »PQ-Box 300« of the PQ-Box family.

Read more

Training Video

»PQMobil« Training Video 1: Getting Started With the PQ-Box

This video shows in detail how to connect the »PQ-Box« and record measurements. The »WinPQ mobil« software is then used to visualize and analyse the measurement data and create a report.

Read more

Special Publication

Ferrari´s Meter vs. Electronic Meter

This technical report analyzes a power measurement at a large industrial customer. The customer records very high currents and fifth harmonic voltages during production time, which leads to poor voltage quality.

Read more

General Knowledge

Residual current

In this article, you will learn about residual current measurement & residual current monitoring and why it is important to measure residual current.

Read more

General Knowledge

Power Quality

Good power quality is characterized by the fact that the mains voltage actually arriving at the consumer matches the mains voltage promised by the utility company.

Read more

General Knowledge

Reactive power – definition, calculation and measurement

The key role of reactive power in electrical engineering: definition, calculation, measurement and the differences to active power and apparent power. Find out how reactive power influences the efficiency of electricity grids and shapes energy transmission.

Read more

General Knowledge

What is apparent power and how is it calculated?

This article addresses the question of what apparent power is and how to calculate it. An understanding of apparent power is crucial for the correct dimensioning of inverters and therefore for the optimum efficiency and performance of photovoltaic systems.

Read more

General Knowledge

Ready for the Smart Grid of the Future?

All information about smart grids/intelligent power grids, the technology behind them, advantages, disadvantages, challenges and current distribution.

Read more

Special Publication

Angle Determination of Voltage and Current Harmonics in Practice

Today's devices and equipment such as switched-mode power supplies, frequency converters, regulated drives, charging devices for e-mobiles or LED lighting work internally with high clock frequencies in order to regulate power efficiently. These can lead to both conducted and field-bound (coupled) influences in the energy grid. In this technical report, we explain how you can detect these sources of interference in the grid using suitable measuring technology.

Read more

General Knowledge

All „Supra“ With Your Grid?

Today's devices and equipment such as switched-mode power supplies, frequency converters, controlled drives, charging devices for e-mobiles or LED lighting work internally with high clock frequencies in order to regulate power efficiently. These can lead to line-borne as well as field-borne (coupled) interference in the power grid. In this technical report, we explain how you can detect these sources of interference in the grid using suitable measurement technology.

Read more

General Knowledge

Power Quality Analysis: Tips and Tricks II

Useful tips & tricks for handling Power Quality measuring devices and typical user errors - now in our two-part article! This article provides further insights and practical tips and application examples for power quality analysis.

Read more

General Knowledge

Power Quality Analysis: Tips and Tricks I

Useful tips & tricks for handling Power Quality measuring devices and typical user errors - now in our two-part article! This article explains tips and tricks for performing power quality measurements. It explains which connection errors can be made and which preliminary considerations should be made before using a measuring device.

Read more

General Knowledge

Four Ways to Measure Current

The following technical report examines various methods for measuring current. It discusses how currents are measured using power analyzers and current clamps. The respective advantages and disadvantages of different technologies such as shunts, normal current clamps, hall effect sensors, etc. ar also evaluated.

Read more

Contact request:



* Mandatory

Your data is being processed

a-eberle kontakt newsletter ×

Our seminars &
webinars

► Register here!

x